Broadway subway completion delayed to 2026 due to summer concrete strike: Ministry | Globalnews.ca

Broadway subway completion delayed to 2026 due to summer concrete strike: Ministry | Globalnews.ca

The scheduled completion date for Vancouver’s Broadway subway has been pushed back to early 2026, the Ministry of Transportation said Thursday. The ministry has pinned the delay on a five-week concrete strike in June, which it said affected the start of tunnel boring. Read more: Meet ‘Elsie’ and ‘Phyllis’: Tunnel-boring machines for Broadway Subway set to launch “As a result, the overall schedule for project completion has been moved from late 2025 into early 2026,” it said in a progress …